Cemflow TOPPING PIGMENTED
Previous product
Next product
Cemflow BASE
 

Cemflow
EXTERIOR TOPPING

POLYMER MODIFIED EXTERIOR SCREED
 

Advantages:

    • Fast Drying Technology
    • Eliminate surface irregularities
    • Dimensionally stable
    • Low Odour & Protein Free
    • Allow vehicles to traffic the surface after only 48 hours at 20°C
    Description:

    Cemflow Exterior Topping is a polymer modified cementitious topping designed to eliminate surface irregularities and smooth internal and external concrete surfaces exposed to industrial traffic.

    Usage

    Cemflow Exterior Topping is supplied as a pre-blended dry powder designed for application between 5mm and 15mm (in one application) to provide an exterior wearing surface.

    Cemflow Exterior Topping is self-smoothing, dimensionally stable and fast drying, allowing vehicles to traffic the surface after only 48 hours at 20°C. 

    Cemflow Exterior Topping can be pumped up to 1000m² per day. When hand applied, coverage of 350m² can be achieved dependent upon manpower and equipment used.

    Materials Supplied 

    25 kg paper sacks.

    Coverage

    A 25 kg bag using 4.00 litres of clean water will yield approx. 14.25 litres.

    A 25 kg pack of Cemflow Topping will cover approximately 2.0m² at 7mm thickness.

    Storage

    Protect from frost and store under dry warehouse conditions at a temperature between 10°C and 30°C.

    Shelf Life

    9 months in unopened bags and stored under good conditions.

    Technical Information

    Working time @ 20°C15 minutes
    Setting time @ 20°C90 minutes
    Foot traffic
    @ 5°C
    @ 20°C

    24 hours
    3 hours
    Compressive Strength (N/mm2)
    EN 12190
    1 day
    7 days
    28 days


    > 20.0
    > 30.0
    > 40.0
    Flexural Strength (N/mm2)
    BN 196-1
    1 day
    7 days
    28 days


    > 5.0
    > 8.0
    > 10.0
    Abrasion resistance
    EN 13892-4
    AR0,5
    (Special)
    Slip resistance
    EN 13036-4
    Dry 63
    Wet 41
    Chloride ion content
    EN 1015-17
    ≤ 0.05%
    Thermal compatibility Part 1
    Freeze-thaw (EN 13687-1)
    ≥ 0.8 N/mm²
    Adhesive bond
    EN 1542
    ≥ 0.8 N/mm²
    Capillary absorption
    EN 13057
    ≥ 0.5 kg.m².h0.5
    Flow properties using 30mm ø x 50mm
    flow ring (EN 12706)
    100 – 115mm
    Consumption per mm thickness1.75 kg/m²
    Application thickness5 - 15 mm

    Application Instructions

    SURFACE PREPARATION

    Concrete and sand / cement screeds must be sound, dry and fully cured (not subject to shrinkage) and any laitance or surface treatments must be removed by mechanical means such as grit blasting. The surface tensile strength of the substrate should be a minimum 1.5 N/mm².

    PRIMING

    It is not usually necessary to prime absorbent surfaces. However, to ensure satisfactory bonding, the prepared surface should be dampened down to minimise pinholing. Ensure that the surface is in a saturated surface dry condition i.e. no visible surface water, prior to application of Cemflow Exterior Topping.

    MIXING 

    PUMP APPLICATION

    Mix the powder and water according to the method recommended by the pump manufacturers. In the case of pumps having a continuous water feed adjust the rate of water flow until the mix is a smooth fluid, uniform grey liquid with no surface separation, producing a flow of approximately 105mm using a 35cc flow ring.

    HAND APPLICATION

    Use a power-whisk fitted in a heavy-duty slow speed electric drill. Mix in the proportion of 25kg of powder to 4.0 - 4.5 litres of potable water. Pour the water into a suitably sized bucket and gradually add the powder while stirring, until a smooth, lump free consistency is achieved.

    APPLICATION

    Pour or pump the mixed material onto the prepared surface and allow to attain a smooth finish. The use of a spiked roller will help eliminate entrapped air and smooth out flow lines. Apply at a thickness between of 5mm to 15mm in one pass only.

    Maintaining a “wet edge” as you work will help to minimise natural colour variations that can occur between sections.

    Extra water should not be added to the mix. If the material thickens before it is applied it should be discarded.

    For thicker applications it is advisable to use the lowest recommended water addition level, to reduce the potential of surface laitance.

    To lay Cemflow Exterior Topping to falls add sufficient water to reach a trowellable consistency.

    PATCH REPAIRS

    Isolated areas up to 50mm in depth can be repaired by adding 12.5 kg of clean, dry, 3 – 6mm aggregate to a 25 kg bag of Cemflow Exterior Topping.

    SEALING

    Cemflow Exterior Topping does not need to be sealed. However if extra protection is required, we recommend the use of Setseal 6.

    JOINTS

    Ensure that all joints subject to movement, i.e. expansion and isolation joints, are carried up through the Cemflow Exterior Topping and filled with a suitable joint sealant.

    CLEANING

    Once mixing and laying are complete, tools should be cleaned immediately after use with cold water.

    PRECAUTIONS

    Do not place when the substrate temperature is below 5°C or when the ambient temperature is 10°C and falling.

    Do not apply in temperatures over 25°C. Protect from direct sun whilst applying and curing.

    Do not apply in excessively windy conditions. Do not apply in rain or when rain is forecast.

    Protect from frost.

    Do not exceed the maximum recommended water content and only use clean potable water.

    Do not apply to Tarmacadam or asphalt surfaces. Avoid cleaning with acidic cleaning solutions.

    HEALTH AND SAFETY

    Refer to the product Material Safety Data Sheets before using Cemflow Exterior Topping.

    GENERAL GUIDANCE
    This data sheet is for general guidance purposes only and may contain information that is inappropriate for certain conditions of use. Accordingly, all recommendations and suggestions are made without guarantee. Further information is available from our Technical Department.


    Download file



    Related products





    Connect with Don Construction Products


      Complaints Record Form

      Customer Satisfaction

    Name *
    Email *
    Phone
    Address
    Subject
    Request  
    Security Code *

    Don Construction Products Ltd.

    Headquarters
    Hawthorn House, Helions Bumpstead Road,
    Haverhill CB9 7AA, United Kingdom;
    Tel: +44 1 4407 66360 
    Fax: +44 1 4407 68897

    Email: sara.harvey@dcp-int.co.uk
    Email: stephen.bird@dcp-int.co.uk